TM 9-6115-668-13
NOTE
Installation procedure for Interlock switch S13 (15), S14 (13) and S15 (11) Is the
same as for Interlock switch S12 (17), described below.
1. Install angle piece (32) on control cabinet connection panel (9) using screws (26).
2. Install two washers (25), two serrated lock washers (24), and two nuts (23) on two screws (26).
3.
Install cable (20), screws (18), and washers (19) on interlock switch S12 (17).
4. Install angle piece:
a. Install angle piece (32) on interlock switch (17).
b.
Install two screws (21) and two serrated lock washers (22) on angle piece (32).
c. Insert screws (26) into control cabinet connection panel (9) and install angle piece (32).
d.
Install designation plate (30) on outside of control cabinet connection panel (9) using two screws (31).
e.
Install two washers (29), two serrated lock washers (28). and two nuts (27) on two screws (31) and tighten
two nuts (27).
5. Install cover (46) on spacers (37) and secure using two nuts (47).
6. Stow prop (5) and close front panel (4).
7. To install unit hood assembly (1) refer to paragraph 4.14.
8. Connect load bank to generator set and perform procedures in paragraph 5.53.
Change 1
5-161