TM 9-6115-660-13&P
5-9
RELAY
BOARD HARNESS W11 MAINTENANCE.
This task covers: a. Test
c. Repair
b. Removal
d. Installation
INITIAL
SETUP
Tools
Equipment
Conditions
General Mechanic’s Tool Kit
Reference
(item 1, appendix B)
Solder
Gun (item 3, appendix B)
Both
generator
sets shut down; paragraph
Crimping Tool, Hand (item 3, appendix B)
2-5.3.3. Trailer handbrakes set, front support
Multimeter
(item 3, appendix B)
leg/landing lowered, and rear
leveling
-support
jack lowered; paragraph 2-3.2.1. Switch box
Materials/Parts
cover open.
Solder
Lock washers
TEST
1. Remove four screws (1, figure 5-13),
lock washers
(2), and flat washers (3), and invert relay board
assembly (4).
2. Refer to
wiring diagram
(figure FO-1) and table 5-2, and perform
continuity
check of relay board
harness W11.
Table 5-2.
Relay
Board Harness Wire List
WIRE NO.
FROM
TO
W11-1
W11-2
W11-3
W11-4
W11-5
W11-6
W11-7
W11-8
W11-9
W11-10
W11-11
W11-12
W11-13
W11-14
W11-15
W11-16
W11-17
W11-18
XK3-2
XK3-3
XK3-4
XK3-5
XK3-6
XK3-7
XK5-2
XK5-3
XK5-4
XK5-5
XK5-6
E-7
XK4-2
XK4-3
XK4-4
XK4-5
XK4-6
XK4-7
TB1-1
TB1-4
TB1-5
TB1-3
TB1-6
TB1-2
TB1-1
TB1-8
TB1-10
TB1-17
TB1-6
E-6
TB1-14
TB1-9
TB1-5
TB1-3
TB1-7
TB1-15
WIRE NO.
FROM
TO
W11-19
R1-1
TB1-17
W11-20
XK6-3
TB1-12
W11-21
XK6-4
TB1-11
W11-22
XK6-5
TB1-16
W11-23
XK6-6
TB1-13
W11-24
XK6-7
TB1-15
W11-25
R1-2
E6
W11-26
R2-2
E3
W11-27
E5
TB1-1
W11-28
E4
TB1-2
W11-29
R2-1
TB1-16
W11-30
E2
TB1-15
W11-31
E1
E4
W11-32
XK5-7
TB1-2
W11-33
E1
TB1-14
W11-34
E8
TB1-18
W11-35
XK6-2
TB1-14
W11-36
E9
E3