Section V. PREVENTIVE MAINTENANCE CHECKS AND SERVICES
Table 4-1. Unit Preventive Maintenance Checks and Services (PMCS). CONT.

Power Plant An/Mjq-18 (Nsn 6115-00-033-1398) (2) Mep-003A 10Kw 60Hz Generator Sets M103A3 2-Wheel, 1-1/2 Ton Modified Trailer Page Navigation
  33    34    35    36    37  38  39    40    41    42    43  
img
.
ARMY TM 5-6115-633-14&P
Table 4-1. Unit Preventive Maintenance Checks and Services (PMCS). CONT.
H Hours of operation
W Weekly
M - Monthlv
S Semiannually
A Annually
(As indicated)
(40 hours)
(100 hours)
(500 hours)
(1000 hours)
Interval
Item
Item to be
no.
Inspected
Procedures
WARNING
Before performing any maintenance
that requires climbing on or under
trailer, set trailer handbrakes, chock
wheels, and lower rear leg prop.
Injury to personnel could result from
trailer suddenly rolling or tipping.
NOTE
Generator set checks and services in
this table are described as performed
on a single generator set. These
procedures must be performed on
each of the two generator sets that
that make up the AN/MJQ-18.
Inspect generator set for fuel and oil
1
Generator Set
leaks, loose or missing components and
hardware, and unusual wear or
deterioration. Clean generator set.
NOTE
Fuel system must be above freezing
temperature when draining water and
sediment from strainer, filters,
and tank.
Fuel Strainer and
Open drains on fuel strainer, and primary
2
Filters
and secondary filters. Drain water and
sediment (para 3-20, TM 5-6115-585-12).
Allow to drain until fuel runs clean.
Fuel Tank
Open drain on fuel tank and drain water
3
and sediment (para 3-13, TM 5-6115-
584-12). Allow to drain until fuels runs
clean,
Change 1 4 - 9