ARMY TM 5-6115-633-14&P
Figure 43. External Fuel Line Connection.
Section Il. MOVEMENT TO A NEW WORKSITE
4-3
Dismantling for Movement. Because the power plant is designed to be mobile, a minimum amount of
effort is required to relocate to a new worksite. Procedures are as follows:
a.
Disconnect power plant from system or equipment being powered.
b.
Disconnect ground cable from source of ground and from power plant GROUND TERMINAL stud. Roll
up cable and store in accessory box.
c.
Using slide hammer, remove ground rod. Disassemble, clean, and stow ground rod in accessory box.
Disconnect power plant from external fuel sources, if applicable.
d.
e.
Stow any remaining authorized equipment in accessory box.
f.
Secure fire extinguishers and fuel cans in their respective mounting brackets.
Lower and secure fitted cover in place on power plant.
g.
h.
Remove locking pin from leg prop assembly on rear of trailer. Swing leg prop back and up into traveling
position and secure with pin.
4-6
Change 2