Inspection and Servicing of Generator Set.
External Fuel Line Connection

Power Plant An/Mjq-18 (Nsn 6115-00-033-1398) (2) Mep-003A 10Kw 60Hz Generator Sets M103A3 2-Wheel, 1-1/2 Ton Modified Trailer Page Navigation
  28    29    30    31    32  33  34    35    36    37    38  
img
. .
ARMY TM 5-6115-633-14&P
Figure 42. Installing Power Plant.
WARNING
Do not operate generator sets until power plant is properly grounded
(paragraph 4-2, b.). Serious injury or death by electrocution can result
from operating an ungrounded power plant.
CAUTION
To avoid damage to equipment, make certain of voltage, frequency, and
phase requirements of load being connected to generator sets.
(6) Refer to data plate on load terminal board cover and toTM 5-6115-585-12. Connect power plant to
system or equipment to be powered.
b. Grounding. Check that generator sets are grounded to GROUND TERMINAL stud on trailer body. Using
ground wire supplied, connect power plant to a suitable ground as described below. The following sources of a good
ground are listed in order of preference.
NOTE
As a substitute for the supplied ground wire, any copper wire of at least
No. 6 AWG may be used.
4-4