TM 9-6115-659-13&P
Section III. OPERATION UNDER USUAL CONDITIONS
2-3
ASSEMBLY AND PREPARATION FOR USE.
2-3.1.
Unpacking the Power Plants/Power Units. Unpacking must be performed by unit level maintenance personnel.
2-3.2
Installation. Before the power plant/power unit is started and operated, it is towed to the worksite and positioned.
2-3.2.1 Positioning Power Plant/Power Unit.
a.
Locate the trailer on as level a surface as possible. This is necessary for efficient operation of the generator
set(s).
WARNING
Do not disconnect trailer from towing vehicle before brakes are set and front landing
leg/support leg are lowered. Failure to observe this WARNING could result in severe
personal injury or death from trailer tipping or rolling.
b.
Using the two handbrake levers, set trailer brakes securely to prevent any movement.
c.
Refer to TM 9-2330-202-14&P for uncoupling AN/MJQ-35 or PU-797 trailer from towing vehicle, TM 9-2330-392-
14&P for uncoupling AN/MJQ-35A or PU-797A trailer from towing vehicle, and TM 9-2330-213-14&P for
uncoupling AN/MJQ-36 trailer from towing vehicle.
d.
Adjust front landing leg using elevation crank to level the trailer.
e.
Pull out pin (1, figure 2-5) that secures rear leveling-support jack (2) in travel position.
Figure 2-5. Rear Leveling-Support Jack.