TM 9-6115-668-131.Set MASTER LOAD switch on load bank to OFF.2. Open “AC Circuit Interrupter” on generator set.3.After a 36-second cool down, turn BLOWER/CONTROL POWER switch on load bank to OFF.4.Set all remaining switches on the load bank to OFF.5.Set all switches on the EPP-III/EPU junction box to OFF.6. Shut down generator set.7.Disconnect load bank cables L1, L2, L3, L0 and generator power and control cables from EPP III/EPU junctionbox. Disconnect all ground cables.5-238Change 1