TM 9-6115-662-13&P
g. Refer to table 5-7 and check continuity for each power lead, W-1 through W-5 (10).
Table 5-7. Input Power Leads.
Wire Identification
From
To
W-1
K1-A1
Unit A Generator Set L1
W-2
K1-B1
Unit A Generator Set L2
W-3
K1-C1
Unit A Generator Set L3
W-4
Switch Box Assembly L0
Unit A Generator Set L4
W-5
BUS BAR
Unit A Generator Set GND
h. Refer to table 5-8 and check continuity for each electrical lead, W-11 through W-16 (17).
Table 5-8. Output Power Leads.
4. Test contactor as
Wire Identification
W-11
W-12
W-13
W-14
W-15
W-16
follows:
From
I
To
K1-A2
K1-B2
K1-C2
K2-A2
K2-B2
K2-C2
Switch Box Assembly L1
Switch Box Assembly L2
Switch Box Assembly L3
Switch Box Assembly L1
Switch Box Assembly L2
Switch Box Assembly L3
a. Using a multimeter, test contactor K1 (16) as follows:
(1) Refer to figure 5-12 and perform following continuity checks. If any multimeter indication is not
correct, replace contactor (paragraph 5-12).
Lead Placement
Contactor Terminals
Multimeter Indication
32 and 33
continuity
21 and 22
open circuit
11 and 12
open circuit
A1 and A2
open circuit
B1 and B2
open circuit
C1 and C2
open circuit
A1 and B1
open circuit
B1 and C1
open circuit
C1 and A1
open circuit
(2) Connect power supply VAC line to terminal X of contactor.
5-20