4-21 TRAILER LIFTING RING MAINTENANCE.
This task covers: a. Removal
b. Installation
INITIAL SETUP
Tools
Equipment Conditions
General Mechanics Tool Kit
Reference
(item 1, appendix B)
Wrench, Torque, 800 Newton-Meter
Trailer handbrakes set, front support
(item 2, appendix
Materials/Parts
Nut, Self-locking
TM 9-6115-660-13&P
4-42
B)
leg/landing leg lowered; and rear
leveling-support jack lowered; paragraph
2-3.2.1.
Personnel Required
Two
REMOVAL
1. Remove self-locking nuts (3, figure 4-21), flat washers (2), screws (1) and
AN/MJQ-37 and AN/MJQ-38 only.
mounting plate (7);
Figure 4-21. Replace Power Plant Trailer Lifting Ring.