TM 9-6115-659-13&P
2. DATA PLATE REPLACEMENT.
a.
Drill out rivets (7) and remove schematic diagram data plate (8).
b.
Position new schematic diagram data plate (8) and secure with blind rivets (7).
3. GASKET REPLACEMENT.
a.
Remove old gasket (10) from switch box and scrape surface to remove old cement.
b.
Cut new gasket material and cement to switch box. Refer to figure G-7, appendix G
4. STUFFING TUBE REPLACEMENT.
a.
Unscrew lock nut (11) from stuffing tube body (12) of stuffing tube and remove from switch box.
b.
Insert stuffing tube body (12) through hole in switch box and secure with locknut (11).
NOTE
Switch box mounting hardware for AN/MJQ-35A (plain nuts, lock washers, flat washers,
and cap screws) differs from that used on other power plants but removal and installation
instructions are similar.
REMOVAL
1.
Remove power cables and ground cable (paragraph 4-12).
2.
Remove four self-locking nuts (3), flat washers (4), and cap screws (6), securing switch box (13) to fender.
Remove switch box (13).
INSTALLATION
1.
Position switch box (13) on trailer fender.
2.
Install four cap screws (6), flat washers (4), and self-locking nuts (3).
3.
Connect power cables and ground cable (paragraph 4-12).
Change 2 4-28