TM 9-6115-658-13&P
5-13
5-10 RELAY MAINTENANCE.
This task covers:
a.
Removal
c. Installation
b.
Test
INITIAL SETUP
Tools
Equipment Conditions
Tool Kit, General Mechanic's
Reference
(item 1, Appendix B)
Multimeter
Both generator sets shut down; paragraph 2-5.3.3.
24 VDC Power Source
Trailer handbrakes set, front support leg/landing low-
ered, and rear leveling-support jack lowered;
Materials/Parts
paragraph 2-3.2.1. Switch box cover open.
Lock washers
REMOVAL
Remove two screws (1, Figure 5-6), washers (2), and relays (3) from relay sockets (4).
Figure 5-6. Relay Removal.