TM 9-6115-668-13
INSTALLATION
1.
Place sling around control cabinet (2) and attach to hoisting device using the same Warnings and
Cautions during the installation.
2.
Lift control cabinet (2) and with the aid of assistants place all cables in the back of the control cabi-
net and place on base frame assembly (75).
3.
Install eight bolts (77) into shock absorber (76) and screw into base frame assembly (75).
4.
Unhook sling from hoisting device and detach from control cabinet (2).
5.
Install washer (41, 43), serrated lock washer (44) and grounding strap (42) on threaded pin (40) and
install on nut (45).
CAUTION
Tighten screws at connections to contactor K1 with torque wrench to
the torque value In table (Item G.1, appendix G).
NOTE
Note the correct sequence when Installing the cables and corrugated
hoses by observing the tags Installed on cables during the removal
procedure.
6.
Install corrugated hose (78) with cables into back panel of control cabinet assembly (2).
7.
Slide nut (63) over cable and screw onto corrugated hose (78).
8.
Place generator cable 79 (62), serrated lock washer (60), and washer (61) on bolt and install nut
(59) onto terminal of load contactor K1 (69).
9.
Install corrugated hose (80) with cables into back panel of control cabinet assembly (2).
10. Slide nut (58) over cable and screw onto corrugated hose (80).
11. Place generator cable 78 (57), serrated lock washer (55), and washer (56) on bolt and install nut
(54) onto terminal of load contactor K1 (69).
12. Install corrugated hose (79) with cables into back panel of control cabinet assembly (2).
13. Slide nut (68) over cable and screw onto corrugated hose (79).
14. Place generator cable 80 (67), serrated lock washer (65), and washer (66) on bolt and install nut
(54) onto terminal of load contactor K1 (69).
15. Install corrugated hose (81) with cables into back panel of control cabinet assembly (2).
16. Slide nut (53) over cable and screw onto corrugated hose (81).
17. Connect cables 77 (48) to K1, 76 (49) to I2, 164 (50) to T2 and 163 (51) to T1 at lower terminals
(47) of connection strip Xl (46).
18. Install cable 141 (52) onto terminal N of control cabinet connection panel (5).
19. Insert generator cable harness (27) into back panel of control cabinet assembly (2), slide nut (26)
over cable and install onto cable union.
20. Connect cables of generator cable harness (27) to input terminal strip (29).
4 - 1 0 9