TM 9-6115-662-13&P
Table 2-2. Operator Preventive Maintenance Checks and Services
for AN/MJQ-40, PU-803, and PU-804 (continued)
Procedure
Not Fully Mission
Capable if:
10
Before
T R A I L E R - c o n t i n u ed
SWITCH BOX ASSEMBLY
(POWER PLANT UNIT A
ONLY)
Visually check for the following:
l
l
l
l
Loose or missing mounting
hardware
Damaged indicator lights
Damaged or missing hinges
latches
Loose or damaged switches
Damaged or missing output
terminals or connectors.
and
Two or more
mounting bolts
missing.
Indicator lights are
damaged.
Switches loose or
damaged.
Output terminal or
connectors will not
secure load cables.
2-15