Item
No.
7
8
9
10
11
12
ARMY TM 9-6115-464-12
AIR FORCE TO 35C2-3-445-1
NAVY NAVFAC P-8-624-12
Table 5-5. Operator Preventive Maintenance Checks and Services For Electric
Interval
After
After
After
After
Weekly
Weekly
Location
Item to
Check/
Service
Power
Cable
Coolant Line
Valves
Generator
Set Radiator
Coolant
Lines
Wiring
Harnesses
Control
Assembly
Winterization Kit - Continued
Procedure
Disconnect after operation (para 5-10).
CIose all coolant line valves after operation
(para 5-10).
Check for proper coolant level after operation.
Check coolant lines for leaks after operation.
Check for frayed insulation and loose connectors or
terminals (para 5-5).
Check for damage and test indicator lights (para 5-13).
Not Mission
Capable If:
5-25