NOTE
Hold the field frame securely on the
armature (36) when placed into the
starter housing (6) so that the field
frame does not slip off. Otherwise
brushes (37) will have to be removed
and re-installed as per step j(4).
(7) Put starter housing (6) in place on field frame.
Ensure that matchmarks are lined up. Secure
starter housing to field frame using machine
bolts (34).
(8) Attach brush leads to brush holders using brush
plate screws (56).
(9) With lip facing lever housing brushing (35),
install a new spacer washer (37) in lever
housing (3).
(10)
Install a new preformed packing (38) on
lever housing (3) and put lever housing in place
on field frame. Ensure that matchmarks are
lined up.
(11)
Install brake washer (30) over shaft of
armature (36), tilt shift lever (11), and install into
lever housing (3). Ensure that shaft lever is
properly positioned in collar of drive assembly
(29).
(12)
Install shift lever shaft (18) with preformed
packings (20 and 19) and secure with new snap
ring (17).
(13)
Using new gasket, put stator housing in
place
on
lever
housing.
Ensure
that
matchmarks are lined up. Install drive housing
bolt (22) and internal housing bolts (23) Cross-
tighten bolts to 13 to 17 footpounds (18 to 23
newtonmeters).
(14)
Place spring retainer washer (16), protector
bellows (8), recessed washer (15), plunger
spring (12), and recessed washer (14) over
plunger (7) and secure with snap ring (13).
(15)
Install plunger (7) through shift lever (11).
Install plunger rod nut (10) on shaft until
several threads are engaged.
(16)
Install electrical solenoid (5) over plunger
(7) and into protector bellows (8).Secure
electrical solenoids to starter housing (6)
with machine bolts (4).
(17)
Place terminal lug (60) on field terminal of
electrical solenoid (5). Install external nut
(40) and tighten it with other hexagonal nut
(41) to 20 to 25 footpounds (27 to 34
newtonmeters).
(18)
Check and adjust pinion and clearance per
paragraph 13-6 (4).
k.
Installation
(1) Install three bolts through housing (21, figure
13-9) to secure starter to engine assembly.
(2) Attach battery cable connections and connect
wires to pilot relay (6, figure 13-4).
13-7.
TACHOMETER DRIVE ADAPTER (Code A).
To replace the tachometer drive adapter, code A,
proceed as follows:
a.
Remove the speed switch in accordance with
the
Operator/
Crew
and
Organizational
Maintenance manual.
b.
Unscrew the adapter (6, figure 13-12) from the
tachometer drive housing.
c.
Replace with a new adapter, if required.
d.
Replace the speed switch in accordance with
the
Operator/
Crew
and
Organizational
Maintenance manual.
13-8.
TACHOMETER DRIVE (Code A). To inspect,
replace, and repair the tachometer drive, refer to figure
13-12
13-21