10-3.
PRELIMINARY PROCEDURES.
Prior to ASK installation, perform the following procedures:
a.
When ASK installation is to be performed on trailer
mounted generator sets, ensure that generator set ground is
connected to trailer ground.
b.
Refer to Operator and Organizational Maintenance
Manual, paragraph 4-17, and remove the grille from the engine
blower housing.
Store grille and attaching hardware at owning
units facility.
10-4.
ACOUSTIC SUPPRESSION KIT INSTALLATION.
a.
Right Support Assembly.
(1) Refer to Operator and Organizational Maintenance
Manual paragraph 4-17, and remove shroud and blower housing.
(2)
Refer to figure 101 and locate right support
assembly (1) on skid (2).
Align slots (3) in support assembly
(1) with existing screw heads (4) and using support assembly (1)
as template, mark the two additional mounting holes (5).
(3)
Drill two 7/16 inch holes (5) into skid (2) for
right support assembly (1).
(4)
Cut a 50 in. length of adhesive backed teflon
tape (listed in Table 10-1, item 1).
Apply adhesive backed
teflon tape to a clean right support assembly top surface
(surface that mounts against underside of skid frame). Use hand
pressure to remove air bubbles.
Clear teflon tape away from
screw slots.
(5)
Loosen four existing screws (4) and slide right
support assembly (1) between skid (2) and bevel washers (6) as
shown in figure 10-1, detail A.
(6)
Install two each screws (7), washers (8), bevel
washers (9), lockwashers (10), and nuts (11) (as listed in Table
10-1, item 1) in the two additional mounting holes (5).
(7)
Torque four existing screws (4) and the two added
screws (7) to 26 ±2 ft-lbs dry.
(8)
Refer to Operator and Organizational Maintenance
Manual, paragraph 4-17, and replace shroud and blower housing.
10-4
Change 6