TM 9-6115-662-13&PSection Il. SERVICE UPON RECEIPT4-4 SERVICE UPON RECEIPT OF MATERIEL.4-4.1 UnpackingPowerUnit.(Refer to figure 4-1 and figure 4-2.) The power unit is boxed prior toshipment. The PU-803 and PU-804 are identical with the exception of the electrical output frequency ofthe generator sets. Two PU-803 Power Units makeup the AN/MJQ-40 power plant. Therefore, theunpacking procedures are typical for each configuration. Each generator set is packed in place on itsrespective trailer. Before beginning the unpacking procedure, locate and remove Depreservation Guide.a. Remove and set aside packing list from side of box. Also remove and set aside shortage packing listif there is one.Figure 4-1. Power Unit Packed for Shipment.4-3