TM 9-6115-659-13&P
i.
Position ground cable (16) over ground stud (17).
WARNING
Ensure nut (14) is properly secured creating a good ground. Failure to observe this
warning could result in severe personal injury or death.
j.
Install flat washer (15), hex nut (14), two flat washers (13), and wing nut (12). Tighten nut (12).
k.
Unlatch and open switch box load terminal cover (18).
l.
Connect ground wire (16) to switch box ground terminal (19).
m.
Close and latch switch box load terminal cover (18).
n.
Position cable and ground wire inside two clamps (10) and secure clamps to trailer using two screws (8), flat
washers (9), and nuts (11).
4-5.2.2
Assembly of Power Plant AN/MJQ-35A. Refer to figure 4-1.1 and assemble the AN/MJQ-35A Power Plant as
follows:
a.
For front generator set, remove stuffing tube locknut (1) from stuffing tube body (7). Slide locknut (1) off power
cable leads and ground cable (3).
b.
Loosen compression nut (4). Pull in required length of cable to allow installation of leads on terminal board.
c.
Insert power cable leads (ends without terminal lugs) (3) through generator output plate (2). Slide stuffing tube
locknut (1) over power cable leads.
d.
Position stuffing tube body (7) against generator output plate (2). Install and tighten stuffing tube locknut (1).
e.
Connect power cable leads and ground cable as follows:
(1)
Connect lead marked L1 to generator set load terminal L1.
(2)
Connect lead marked L2 to generator set load terminal L2.
(3)
Connect lead marked L3 to generator set load terminal L3.
(4)
Connect lead marked LO to generator set load terminal LO.
(5)
Connect lead marked GND to generator set GND terminal.
f.
Position cable inside two clamps (10) and secure clamps (10) to trailer using two screws (8), flat washers (9), and
nuts (11).
g.
Repeat steps a. through e. for rear generator set.
Change 2 4-6