TM 5-6115-584-34
NAVFAC P-8-622-34
TO-35C2-3-456-2
(2) Perform the test and calibration procedures
shown in figure 6-4.
(3) Failure of the voltage regulator to meet the test
and calibration requirements indicates the voltage regulator
should be replaced.
e. Repair. See voltage regulator schematic diagram,
figure 6-5 or 6-5.1.
(1) Repair of the voltage regulator is limited to
replacing defective components. Refer to the schematic fig-
ure 6-5 or 6-5.1 for proper values.
f. Installation (see figure 6-3).
NOTE
When replacing voltage regulator, remove
jumpers first from old voltage regulator. Install
jumpers in the same location on the new regula-
tor. Failure to do so will result in voltage regulator
failure. If difficulty occurs in reconnecting
jumpers, refer to Fig 1-1.
(1) Mount serviceable voltage regulator (39) into
the control box (57) using nuts (38).
(2) Reconnect previously tagged and removed har-
ness to the voltage regulator terminal board.
6-7. AC OUTPUT CONTROL BOX WIRING HARNESS.
Install and repair wiring harness by replacing wires, connec-
tors, and terminal lugs as necessary. See figure 6-6 and tables
6-3,6-3.1 for all necessary wiring harness assembly.
6-8. AC OUTPUT CONTROL BOX ASSEMBLY.
a. Test, on Equipment.
(1) Resistor R3 (20, figure 6-10) must be adjusted
as follows before performing any tests.
(2) Remove wire D26F16 from TB3-1 and con-
nect 0 to 1 amp ac ammeter. Connect test ammeter as shown
in figure 6-7.
(3) Place reconnection switch in 120
position.
(4) With the generator operating at rated fre-
quency, apply rated load by closing circuit breaker (CB1) (9,
figure 6-10).
(5) Adjust R3 until ammeter previously installed
reads 0.6 amps, tighten locknut on R3. R3 is now adjusted
properly.
(6) Disconnect test equipment and proceed with
testing in accordance with test schedule.
NOTE
Because the proper connection of certain ac out-
put control box circuits can only be determined
by its ability to function properly when operated
in conjunction with the control cubicle, it is
imperative that the control cubicle supplied be
complete and is functioning properly for all
tests.
(7) With the unit running normally, test control
box assembly by measuring voltage at load terminals with
the reconnection switch in each of its three positions. See
table 6-4.
b. Remove (see figure 6-8). Remove electrical connec-
tor plugs from connectors (2) on side of control box (1).
Remove two screws (3), lockwashers (4), bevel washers (5),
lockwashers (6), and nuts (7). Remove four screws (8) and
washers (9) attaching box to skid-base (10) and remove con-
trol box (1).
c. Install. Mount control box (1) to skid-base (10)
using screws (8), washers (9), and screws (3), lockwashers (4),
bevel washers (5), lockwashers (6), and nuts (7). Reconnect
plugs to connectors (2).
6-9. AC OUTPUT CONTROL BOX (INTERNAL
COMPONENTS).
Before working on the load terminal board or
other devices associated with the ac control box,
make certain that the Generator Set is not oper-
ating, all switches are in the OFF or OPEN posi-
tion, and there is no input to the load.
Table 6-4. Terminal Voltages
Measure
Correct
Switch Position
Across
Voltage
120 V, 1 Phase
L1-L3
120 vac
120/240V, 1 Phase
L0-L1
120 vac
L0-L3
120 vac
LI-L3
240 vac
120/208V, 3 Phase
L0-L1
120 vac
L0-L2
120 vac
L0-L3
120 vac
L1-L2
208 vac
L2-L3
208 vac
LI-L3
208 vac
Change 7
6-9