TM 5-6115-376-13
Section Il. MOVEMENT TO NEW WORKSITE
PU-699/M trailer to PU-700/M truck). Place
front and rear landing legs of trailer sets in
Stop all units, disconnect power cables between
stored position, and ladder in place on truck.
units; wind the 100-foot power cables on their
Attach air and electric lines between trailer and
reels, and store reels in travel position (2 on
truck, close truck tailgate.
PU-407/M and PU-699/M, 18 on PU-408/M and
PU-700/M). Disconect ground rods and auxiliary
2-9. Reinstallation After Movement
fuel drums (if used). Close up distribution panel
Following movement, separate trailer and truck
assemblies, DE hoods, and reinstall switchbox on
fender of PU-699/M (or synchronizer assembly
connections (para 2-4) and external fuel lines
on fender of PU-407/M ). Store portable acces-
sory boxes, fuel cans, and portable distribution
sets, panels and auxiliary facilities (para 2-5
boxes in place on trailer and truck. Hook the
through 2-7).
PU-407/M to rear hitch of PU-408/M truck (or
Section Ill. CONTROLS AND INSTRUMENTS
for the PU-407/M setup ready for operation,
This section describes the various controls and
Function
Control, Indicator, or Connector
instruments, and provides the operator/crew
Phase meters, one per phase, ___ Indicate total phase cur-
sufficient information to insure proper operations
rent drain of the three
of the two generator sets.
(PU-407/M and PU-408/M) associated single phase
power circuits,
0-500 amps (PU-699/M and
PU-700/M).
2-11. Controls and Instruments
Phase control switches _ _Provide on-off contact and
overload protection for
(circuit breaker switches
The following are descriptions and functions of
associated single phase
with 70-amp rating, 3 per
the controls, indicators, and connection points of
power circuits.
phase).
the power distribution components of the trailer
Phase indicator lamps _______Glow when associated
mounted (PU-407/M or PU-699/M) or truck
phase circuit breaker
(neon lamps 110 VAC, 3
switch is operated to on
per phase).
position.
sets. For information concerning controls and
Phase receptacle-connector ____ Provide for connection of
instruments on the diesel engine generator units,
output power cables to
(power receptacle-connec-
refer to TM 5-6115-239-10 (Consolidated Model
single phase power cir-
tor, 3 per phase).
4070, 45KW) or to TM 5-6115-247-15 (Stewart-
cuits.
Stevenson Model 54400, 45KW). For the 60KW
b. Portable Distribution Boxes (AU Units).
sets refer to TM 5-6115-425-23. For information
on the M54A2 cargo truck refer to TM 9-2320-
Functions
Control, Indicator, or Connector
211-10; and for information on the M200A1 gen-
Control switches (circuit ______ Provide on-off control and
overload protection for
breaker switches, 15-amp
erator trailer refer to TM 9-2330-205-14. Figure
associated power recep-
rating).
2-5 shows a
typical control panel set up. (Model
tacle (No. 1 through
4070 shown; other models have similar controls),
No. *).
Indicator lamps (neon, _____ __Glow when associated
a. Distribution Box (All Units). The descrip-
110 VAC).
control switch is oper-
tions and functions listed below apply to controls,
ated to On position.
indicators, and receptacle connectors associated
Output receptacles (Duplex---- Provide for connection or
with all three output phases (A, B, and C) of the
tional or special equip-
distribution box of the PU-407/M and PU-408/M,
ment
The distribution box, distribution panel, and con-
Input Receptacle Connectors--- Provide for connection of
trol panel used with the 60KW PU-699-M and
power cable from distri-
PU-700/M is similar, differences being in com-
bution box.